New Towne Lake Water Well

Residents of HC433 in sections 10, 15, 17 & 20:

Towne Lake (Harris County MUD 500) and Alsay Incorporated are in the process of drilling a new water well at the water plant site located at 111 Tuckerton Road. The water well drilling process requires big equipment that can be loud during certain tasks being performed. In order to try our best to reduce the noise to not disturb those around the work area a sound wall has been put up between the HC MUD 500 Water Plant and HC MUD 433 Wastewater Treatment Facility.

Below is the tentative construction schedule of when they plan on completing each portion of this job. The highlighted items could require overnight work: